PRA Builder
Projects
Risk Library
High-Risk Work Items
Edit Library Risk
Library risks are templates. Project copies can be edited independently.
Section
Choose section
PRE-CONSTRUCTION / 1. BRIEF
PRE-CONSTRUCTION / 2. DESIGN
PRE-CONSTRUCTION / 3. CONSULTANTS
PRE-CONSTRUCTION / 4. PROGRAM
PRE-CONSTRUCTION / 5. APPROVALS
PRE-CONSTRUCTION / 6. EXISTING BUILDING
PRE-CONSTRUCTION / 7. INSURANCES
PRE-CONSTRUCTION / 8. CONTRACTORS
PRE-CONSTRUCTION / 9. MAINTENANCE
PRE-CONSTRUCTION / 10. BUILDABILITY
PRE-CONSTRUCTION / 11. INDUSTRIAL
PRE-CONSTRUCTION / 12. HEALTH SURVEILLANCE
CONSTRUCTION / 1. EMERGENCY PLANNING
CONSTRUCTION / 2. PUBLIC DEMONSTRATION
CONSTRUCTION / 3. SITE ESTABLISHMENT
CONSTRUCTION / 4. ACCESS / EGRESS & HOUSEKEEPING
CONSTRUCTION / 5. CAR PARKING AND PEDESTRIAN MOVEMENT
CONSTRUCTION / 6. TRAFFIC
CONSTRUCTION / 7. EMERGENCY VEHICLES
CONSTRUCTION / 8. SEGREGATION
CONSTRUCTION / 9. PUBLIC PROTECTION
CONSTRUCTION / 10. MANUAL HANDLING
CONSTRUCTION / 11. NOISE
CONSTRUCTION / 12. WORKING AT HEIGHTS
CONSTRUCTION / 13. PENETRATIONS
CONSTRUCTION / 14. FALLING OBJECTS
CONSTRUCTION / 15. CRANES
CONSTRUCTION / 16. CONCRETE PUMPS
CONSTRUCTION / 17. INSTALLING TILT UP OR PRE-CAST CONCRETE PANELS
CONSTRUCTION / 18. INSTALLING HANDRAILS & TEMPORARY EDGE PROTECTION
CONSTRUCTION / 19. WORK ON OR NEAR CHEMICAL, FUEL OR REFRIGERANT LINES
CONSTRUCTION / 20. USING A MOBILE SCAFFOLD / EWP
CONSTRUCTION / 21. CONFINED SPACES
CONSTRUCTION / 22. WORK ON OR NEAR PRESSURISED GAS PIPES OR MAINS
CONSTRUCTION / 23. ELECTRICAL WORK
CONSTRUCTION / 24. ELECTRICAL ISOLATION
CONSTRUCTION / 25. ELECTRICAL RE-ENERGISATION
CONSTRUCTION / 26. USING ELECTRICAL TOOLS
CONSTRUCTION / 27. ASBESTOS
CONSTRUCTION / 28. USE OF HAZARDOUS CHEMICALS / SUBSTANCES
CONSTRUCTION / 29. ERECTING SITE FENCING
CONSTRUCTION / 30. MOBILE PLANT
CONSTRUCTION / 31. USE OF TOOLS / MACHINERY (Minor Plant)
CONSTRUCTION / 32. WORKERS IN AREAS OF HEAVY PLANT / VEHICLE MOVEMENT
CONSTRUCTION / 33. WORKING ON OR NEAR PUBLIC ROADS
CONSTRUCTION / 34. WORKING ON OR NEAR WATER
CONSTRUCTION / 35. EXCAVATIONS
CONSTRUCTION / 36. EXTREME HEAT
CONSTRUCTION / 37. ENVIRONMENTAL
CONSTRUCTION / 38. SUBSTATIONS WORKS (Installation or Removal)
CONSTRUCTION / 39. WORK ON OR NEAR ENERGISED ELECTRICAL INSTALLATIONS OR SERVICES
CONSTRUCTION / 40. SHIPPING CONTAINERS AND SITE SHEDS
CONSTRUCTION / 41. DELIVERY / REMOVAL
CONSTRUCTION / 42. DAILY USE
CONSTRUCTION / 43. TREE REMOVAL
CONSTRUCTION / 44. DEMOLITION
CONSTRUCTION / 45. BULK EARTHWORKS
CONSTRUCTION / 46. DETAILED EARTHWORKS / DRAINAGE
CONSTRUCTION / 47. INSTALLING ELECTRICITY TO SITE SHED AND TEMPORARY BOARDS FOR WORK SITE
CONSTRUCTION / 48. FORMWORK
CONSTRUCTION / 49. REINFORCEMENT
CONSTRUCTION / 50. POST TENSIONING (PT)
CONSTRUCTION / 51. CONCRETE POURS
CONSTRUCTION / 52. SCAFFOLD
CONSTRUCTION / 53. WELDING
CONSTRUCTION / 54. STRUCTURAL STEEL
CONSTRUCTION / 55. BLOCKWORK / BRICKWORK / ROCK WALLS
CONSTRUCTION / 56. LIFT CONSTRUCTION
CONSTRUCTION / 57. WATERPROOFING
CONSTRUCTION / 58. RENDER
CONSTRUCTION / 59. ALUCABOND OR SIMILAR
CONSTRUCTION / 60. ROOF TRUSSES
CONSTRUCTION / 61. METAL ROOFER
CONSTRUCTION / 62. ROOF TILING
CONSTRUCTION / 63. MEMBRANE
CONSTRUCTION / 64. SOFFIT
CONSTRUCTION / 65. ROOF RESTRAINT SYSTEM
CONSTRUCTION / 66. SPRINKLERS
CONSTRUCTION / 67. FIRE SERVICES
CONSTRUCTION / 68. HYDRAULIC SERVICES
CONSTRUCTION / 69. SECURITY
CONSTRUCTION / 70. DATA
CONSTRUCTION / 71. MECHANICAL
CONSTRUCTION / 72. DRY WALLS AND CEILINGS
CONSTRUCTION / 73. CARPENTRY FIX
CONSTRUCTION / 74. SUNSHADES
CONSTRUCTION / 75. WINDOWS AND DOORS
CONSTRUCTION / 76. PAINTER
CONSTRUCTION / 77. GLAZIER
CONSTRUCTION / 78. JOINERY
CONSTRUCTION / 79. TOILET PARTITIONS
CONSTRUCTION / 80. FLOORING CARPET / VINYL
CONSTRUCTION / 81. FLOORING TIMBER
CONSTRUCTION / 82. CERAMIC TILING
CONSTRUCTION / 83. BLINDS
CONSTRUCTION / 84. HANDRAILS / METALWORK
CONSTRUCTION / 85. SIGNAGE
CONSTRUCTION / 86. BITUMEN PAVING
CONSTRUCTION / 87. LANDSCAPING
CONSTRUCTION / 88. FINAL CLEAN
CONSTRUCTION / 89. PERSONAL HAZARDS
CONSTRUCTION / 90. PLANT / MACHINERY
CONSTRUCTION / 91. SUPERVISION OF APPRENTICES (APPRENTICES, TRAINEES & YOUNG WORKERS)
POST CONSTRUCTION / 1. COMMISSION PLANT
POST CONSTRUCTION / 2. BUILDING MAINTAINABILITY
Hazard / risk
Severe Crush Injuries Falling Panels Electric Shock
Default risk level
Default residual risk
Default control measure
A Temporary Traffic Management (TTM) Plan is required for vehicles to safely enter and leave the site without disrupting the normal flow of traffic. An area for the unloading of the precast elements to be designated. If the design envelope of the plant encroaches into any electrical ???No Go Zone??? an alternative safe system of work to be developed in line with the Framework for Undertaking Work Near Overhead and Underground Assets, including requirements for a qualified spotter. SBG and erector/installer need to discuss if any back filled excavations or suspended slab areas are on site. Verification that the erection platform can safely carry the construction and erection loads. The area/s designated for the unloading of precast panels must be firm and level. Shop drawings for all precast elements are to be available on site. The shop drawings have been reviewed, by the Project Design Engineer and signed off by the Erection Design Engineer. SBG must obtain from the Erection Design Engineer a certificate of compliance, advising that all elements have been designed in line with the Australian & Industry Standards. All lateral restraints (dowel bars, angle irons etc.) must be installed and fixed in position during the erection of the precast concrete elements as per the design engineer???s detail. A Manufacturers Certificate of Compliance (Birth Certificate) to be developed by the precast company, for each of the panels being erected on site. The Manufacturers Certificate of Compliance (Birth Certificate) must be available on site for review prior to installation. A Safe Work Method Statement (SWMS) to be prepared for the works. Prop requirements, including positions to be detailed on shop drawings for each individual precast element on site. If temporary supports such as angle brackets are to be utilised to support panels prior to permanent fixings being installed, have engineers provided detail of the temporary supports. There needs to be a toolbox talk between the SBG Project Supervisor and the crane & install crew to discuss the location of the crane and to identify any backfilled areas, excavations or underground services which may be present on site. The rigging details to be available for panels to be erected on site. Appropriately qualified persons to undertake the erection of panels on site. (Advanced/Intermediate Rigging, RA, RI) Appropriately Licensed Crane Operator. The precast elements are to be rotated on site by a single crane to their final position for installation, 75% of the total weight of the lift needs to be supported by the tailing lifter and the auxiliary winch. If alternative locations are to be utilised for the bracing of precast components on site, SBG must obtain written approval from an engineer in relation to the type and position of the new brace points. If lifting points are identified that are incorrectly installed, damaged, or missed during manufacture of the precast element, alternate lifting points to be designed by the Erection Design Engineer. SBG must obtain from the project design engineer or suitably qualified independent engineer, written approval to remove temporary bracing. The written approval from the Erection Design Engineer must state that all permanent connections have been inspected and approved.
Default responsible party
Tags
High-risk category
Active
Save Library Risk
Cancel